A dry-process cement facility was experiencing recurring wet dust buildup at the bottom of its gas cooling tower (GCT). The buildup contributed to unstable preheater gas temperatures, process upsets, raw mill interruptions, and elevated baghouse maintenance. Lechler worked with the plant to optimize the existing gas cooling system by improving atomization, tightening temperature control, and significantly reducing compressed air demand.
Following installation and commissioning in August 2025, the site reduced compressed air usage for the gas cooling system from about 700 SCFM to approximately 205 SCFM, while stabilizing GCT outlet temperature control near a 320°F (150°C) target.
Industry: Cement manufacturing
Application: Gas cooling tower on preheater exit gas (upstream of raw mill and dust collection)
Primary challenge: Wet dust buildup, temperature instability, and high compressed air consumption
Target conditions: Inlet gas typically ~820 to 840°F, outlet temperature target 320°F (150°C)
Lechler solution:VarioCool® nozzle-lances with protection tubes, upgraded measurement, and optimized control strategy
Commissioning: Completed within 48 hours after installation (during a planned shutdown)
Payback: Less than 10 months (as reported by the project team)

Operations and maintenance teams were dealing with:
A Lechler engineering review found that instability was driven by a combination of:
Lechler completed an assessment that included a heat balance and a review of spray performance, nozzle placement, and control response.
Key design inputs used for sizing and verification:
The team also identified opportunities to reduce compressed air consumption through improved atomization efficiency and by adding instrumentation to verify air and water delivery across operating conditions.
The retrofit focused on three areas: spray performance, measurement, and controls.
Spray system upgrades
Instrumentation and controls
Execution and validation
Performance summary:
Metric | Before | After |
Compressed air demand (GCT spray system) | 700 SCFM | ~205 SCFM |
Reduction in compressed air demand | ~71% | |
Outlet temperature behavior | ~450°F typical with instability | 320°F setpoint with stable control |
Operator intervention | Frequent | Routine monitoring |


Key takeaway: Nozzle selection, atomization quality, and control response work as a system. Improving droplet distribution reduced wall wetting, which reduced buildup and stabilized operation while cutting operating cost.
This retrofit approach is well-suited for cement plants facing: